Tucker Avenue Reconstruction Project – Phase 1

Tucker Ave. is closed to traffic for extended periods on Thursday July 21. Local access will be interrupted.

Tucker Ave. is closed to traffic for extended periods on Thursday July 21. Local access will be interrupted.

Project task(s):

The Contractor will pour concrete curb and gutter on both sides of the street. Crews will start with street intersections, then proceed to driveway entrances in preparation for new sidewalk.

Local Access Interruptions:

Residents and businesses are asked to anticipate a single interruption to vehicle access lasting approximately 3 to 4 hours. This interruption will occur during regular construction hours as crews work past driveway entrances. The Town or Contractor will attempt to notify effected building occupants at least one hour prior.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

Please prepare for this interruption by moving your vehicle outside of the construction zone. Work will occur as quickly as possible. Cement will require a minimum of 2 hours to dry and cure. The Contractor will install ramps when and where possible.

Street Closure:

Tucker Avenue will be temporarily closed throughout the day on Thursday, July 21, 2016 between 7:00 a.m. and 6:00 p.m. for equipment operation. Southbound traffic should anticipate 20-minute delays when open.

Detour:

Traffic will be rerouted using Harbor Avenue, in addition to the established detour route. Flaggers will advise drivers when use of Harbor Street is appropriate. Vehicles are asked to help ease congestion by using the detour route.