San Juan County’s Public Works Department is kicking off the Douglas/Bailer Hill Road Improvements Project this month and is sharing safety reminders for drivers.

Throughout the length of the project, vehicle speeds will be reduced to 35 mph in the construction zone. This area spans from approximately the intersection of Little Road and Douglas Road, up through a section of Bailer Hill Road. Signage will be posted.

Go Slow Zone

In addition, please remember to drive slowly through active construction zones:

For their safety: you are driving through an active construction zone – obey flaggers and posted traffic signs.

For your safety: excessive speeds may kick up loose rock into oncoming traffic.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

It’s your road: construction can move more quickly and safely when vehicle speeds are reduced.

Project Details

The 1.3-mile project is anticipated to last through September. The existing road will remain open to through traffic and the project is not anticipating a full closure or detour. During working hours, flaggers will manage single-lane access as needed and reopen the road fully during evenings and weekends. The project team is coordinating with the school district, first responders, and other partners to provide project details and ensure continuation of services.

The project, funded by the County Road Administration Board and the SJC Roads Fund, seeks to:

Eliminate horizontal and vertical sight distance issues by smoothing peaks and valleys

Add paved, four-foot shoulders on both sides of the road along the length of the project to provide safety accommodations for bicycle and pedestrian traffic

Construct a ‘Radial-T’ intersection leading to the Oaks housing development, eliminating the two existing ‘dog legs’ at the intersection that create sight line issues

Raise the elevation of Bailer Hill Rd to minimize seasonal flooding

Improve roadway drainage with wider ditches and upsized driveway culverts for adjacent homes

Improve stormwater quality by adding vegetated filter strips along roadway edges

The Public Works Department will continue to provide updates as the project moves forward. All related materials can be found on the County’s website: https://www.sanjuancountywa.gov/278/Current-Projects.