Chipseal will begin on May 18, 2016 and will continue until anticipated project completion of June 10, 2016. The schedule of roads to be sealed is below. Be advised that this schedule is subject to change due to weather and equipment needs. You can check back here for updates. The 2016 Chipseal Map can be found under the Public Works Quick Links.
Week of May 18
Cattle Point Rd –approximately 1 mile beginning at Fish Creek
Week of May 23
Cattle Point Rd -continuing to False Bay
Eagle Cove Rd
False Bay Dr
Bailer Hill Rd between Douglas Rd and Bolin Retreat Rd
Kanaka Bay Rd – section near Bailer Hill Rd
Week of June 6
Jensen Bay Rd from Jensen Bay to Cattle Point Rd
Halsey Rd
Portland Fair Rd
Aquilla Rd
Cattle Point Rd between Little Rd and False Bay
Little Rd
Madden Ln
Douglas Rd
San Juan Valley Rd (areas near Valley Farms Rd and Emmerling Pl.)
Mill St.
Wilks Way
MacGinitie Rd
Boyce Rd.
Wold Rd.
Bailer Hill Rd between Bolin Retreat Rd and Wold Rd